- Monday/Tuesday: Dry wall will be completed

- Monday/Tuesday: Grading and berm will be complete

- Thursday:  First coat of paint will start

- Thursday/Friday: Non-laminate floors/tile will be put in

Side notes:

Not much happened this week, just the dry wall and I think we got gutters too.  It's been going slowly compared to the other steps of the house being built, which makes even harder on the wait until it's complete lol.  We can't wait to see the berm and grading complete and our PM said to call if we don't like it or if we think it should be changed after we see it complete.  It's nice that he is considering our input when completing this.

Also our PM said one of our neighbors doesn't want trees on the berm and they are still figuring out what to do about that, but we will be getting trees behind our house either way.  I'm not sure why they wouldn't want free trees, especially seeing how there is a 30 mph road behind the berm and the trees are for blocking the sound/site of the cars.  Really weird, but doesn't effect us just the neighborhood as a hole.  Hopefully they don't just stop the tree line for that house, but I'm not sure what else they are going to do.

No comments:

Post a Comment