Our Weekly Update from Our PM:
-As of Today: foundation and waterproof are done
-Today May 9: running water lines for gutters to drain into (our gutters go into ground lines that drain into neighborhood pond)
-Monday May 12: back filling dirt
-Tuesday May 13: pouring slab for our garage (weather permitting)
-Tuesday May 13: meeting with town about burm
note: will be flatting and moving closer to road (all neighbors agree with this)
-Wednesday May 14: lumber delivered
-Monday May 19: framing starts
No comments: